Answer :
Final answer:
The duration of the project based on the original estimate of work hours would be approximately 21.44 weeks.
Explanation:
To calculate the duration of the project based on the original estimate of work hours, we can use the formula:
Duration = (Total estimated work hours / Work completed per week) * (100 / Completion percentage)
Given:
- Total estimated work hours: 3,860
- Number of engineers working full time: 4
- Number of hours worked by each full-time engineer per week: 8 hours/day * 5 days/week = 40 hours/week
- Number of engineers working half-time: 1
- Number of hours worked by the half-time engineer per week: 4 hours/day * 5 days/week = 20 hours/week
- Cost per hour for each engineer: $30
- Completion percentage: 65%
First, let's calculate the total work completed per week:
Total work completed per week = (Number of full-time engineers * Hours worked by each full-time engineer per week) + (Number of half-time engineers * Hours worked by the half-time engineer per week)
Total work completed per week = (4 * 40) + (1 * 20) = 160 + 20 = 180 hours
Now, let's calculate the duration of the project:
Duration = (Total estimated work hours / Total work completed per week) * (100 / Completion percentage)
Duration = (3,860 / 180) * (100 / 65)
Duration = 21.44 weeks (rounded to two decimal places)
Learn more about project duration here:
https://brainly.com/question/33393516